<< Click to Display Table of Contents >> Supersequence Steep Dip. |
|
Capital a necessary Subsequences created will now assemble Supersequence to excavate the steeply dipping pit.
The excavation of the steeply dipping Pit will be conducted by the following sequence:
•The initial waste Subsequences will be excavated sequentially until coal is some uncovered.
•The first coal Subsequence for this bench will then be excavated.
•The the waste pass for the following bench will be excavated uncovering some or coal.
•Exposed coal will be excavated to the current bench level.
•The above process will repeat until the strip is complete.
The following video clip illustrates the assembly and excavation of the Supersequence:
Load the File Steep Dip Topic2_Complete.3dd, when the exercise is complete save the 3d-DigPlus file under the name: Steep Dip Topic3_Complete.3dd
3d-DigPlus must be in Auto mode after the tutorial file is loaded:
Simulation Pulldown - Auto Mode
Save the 3d-DigPlus file as:
Steep_Dip_Topic3_Complete.3dd