Dragline Report Window

<< Click to Display Table of Contents >>

Navigation:  »No topics above this level«

Dragline Report Window

Return to chapter overview

Dragline Report Window

Top

Dragline Report

This dialog box shows the simulation report for all simulation steps associated with the current dragline mode simulation.

Close Button

The button closes this dialog box.

Save to File Button

Click this this button to save dragline simulation report to a file.

Delete Button

This button deletes all selected records (strings of the table) from the dragline simulation report.

Print Button

Click this button to print dragline simulation report.

Table

The simulation report is presented in a table format. Each line in the table shows the simulation report for one step. The data reported in the columns of the table are explaned below.

Drag. Number

This is the number of the dragline used in simulation step.

Dragline Name

This shows the name of the dragline used in simulation step.

Dig Method

This is the dig method (dragline setting) current for the step.

Dragline Position X

This column shows the east coordinate of the dragline tub centre for the current step.

Dragline Position Y

This column shows the north coordinate of the dragline tub centre for the current step.

Dragline Position Z

This column shows the reduced level (RL) of the dragline tub centre for the current step.

Max. Dig Depth

This column shows the vertical distance between the dragline operating level and the deepest part of the excavation.

Max. Dump Heigt

This is the vertical distance between the dragline operating level and the highest dump point.

Average Swing Angle

This is the average of the swing angles of all swings in the simulation.

Fraction Rehandle

This is the relation in percents of the total volume to the rehandle volume.

Volume/Dig Hour

This is the total volume divided by the dig hours. It is reported in bank cubic metres or bank cubic yards per dig hour.

Volume/Elapsed Hour

This is the total volume divided by the elapsed hours. It is reported in bank cubic metres or bank cubic yards per elapsed hour. Elapsed hours are the dig hours divided by availability factor.

Average Cycle Time

This is the total cycle time divided by the number of cycles. It is reported in seconds.

Excavate Time

This is the total operating time in hours and minutes for the simulation.